UK completes Wigan–Bolton rail electrification

· Transport / rail

Location
Wigan–Bolton, Greater Manchester (North West England) · 🇬🇧 United Kingdom
Project
Wigan–Bolton railway electrification
Investment
GBP 100 million (Department for Transport)
Status
Completed / electrified

The 6.5-mile (about 10.5 km) line between Wigan and Bolton was electrified for £100 million, with the overhead lines entering service overnight on 26 July 2025. Since construction began in 2022 the scheme delivered 21 km of overhead line equipment and 414 stanchions, rebuilt six bridges, modified 17 further bridges and two level crossings, and extended platforms at Westhoughton, Hindley and Ince stations. It was funded by the Department for Transport and delivered by Network Rail.

Source: networkrailmediacentre.co.uk ↗ · Archived copy ↗