Triton Knoll wind farm off Lincolnshire officially commissioned
- Location
- North Sea, roughly 33 km off the coast of Lincolnshire, England · 🇬🇧 United Kingdom
- Project
- Triton Knoll Offshore Wind Farm
- Investment
- approximately GBP 2 billion (as of September 2021, for the realised 857 MW installation; an earlier 2015 planning estimate for a larger scheme was GBP 3-4 billion)
- Status
- Operational
Triton Knoll is located in the North Sea about 33 km off the coast of Lincolnshire and generates 857 MW of installed capacity via 90 MHI Vestas V164-9.5MW turbines. First power was generated in March 2021, with the final turbine installed in September 2021 and official commissioning in January 2022. The wind farm is operated by RWE (59%), J-Power (25%) and Kansai Electric Power (16%).
Source: en.wikipedia.org ↗ · Archived copy ↗