Tallinn Airport starts €75m expansion to double capacity

· Transport / airport

Location
Tallinn · 🇪🇪 Estonia
Project
Terminal expansion at Tallinn Airport
Investment
€75m
Status
Under construction, four phases 2026-2028

Tallinn Airport starts its largest-ever investment: the terminal grows by about 16,500 m² of new space and 18,000 m² of renovation to a total of 52,500 m², annual capacity rises from 2.8 to up to 5.5 million passengers, and the baggage system gets five belts instead of three. Construction runs from 2026 to 2028 in four phases, the first of which began at the end of 2025; 31 Dec 2028 marks the end of the construction phases and is a placeholder. Announced on 10 Dec 2025 (Invest in Estonia, 10 Dec 2025).

Source: investinestonia.com ↗ · Archived copy ↗

Evidence: one source · archived copy saved · How well sourced is Eurotrack?