Kyiv Metro Line 4 construction largely suspended
- Location
- Kyiv: Podil district / Rybalskyi Peninsula – Trukhaniv Island – left-bank area toward Troieshchyna · 🇺🇦 Ukraine
- Project
- Kyiv Metro, Line 4 (Podilsko–Vyhurivska line) – Sudnobudivna–Zatoka Desenka section
- Investment
- Approximately EUR 1.5 billion (roughly UAH 68 billion, as of 2025) for the entire first construction stage of six stations on the line; no separate figure is available for this specific sub-segment (3 stations).
- Status
- Under construction (works largely suspended per press reports) – completion date uncertain
The Podilsko–Vyhurivska line (Kyiv Metro Line 4) is planned to comprise six stations over about 7.2 km in its first construction stage, including the section examined here between the stations Sudnobudivna, Trukhaniv Island and Zatoka Desenka, which cross the Podilskyi Bridge to link the Rybalskyi Peninsula with the left bank of the Dnipro. The three stations' shell structures (platforms, bridge framework) are largely complete, but the city's 2024 development programme now projects completion of this first stage only by 2033, after earlier target dates (including December 2022) were repeatedly missed. Press reports from June 2025 even question whether completion by 2030 is realistic, citing a lack of active construction work and secured financing.
Source: en.wikipedia.org ↗ · Archived copy ↗
Evidence: one source · archived copy saved · second source missing (two-source rule) · How well sourced is Eurotrack?
More from: 🇺🇦 Ukraine