Správa železnic to build Ruzyně–Kladno line for EUR 340 million by 2029
- Location
- Praha-Ruzyně – Kladno (Central Bohemia) · 🇨🇿 Czech Republic
- Project
- Praha – Letiště – Kladno: upgrade of the Praha-Ruzyně–Kladno line (15 km, largely on a new alignment, double-track, electrified)
- Investment
- CZK 8.279 billion (approx. EUR 340 million), lowest bid in the tender
- Status
- Under construction (contract signed, works due to start in spring 2026, building period to 2029)
Správa železnic has signed the construction contract for the 15 km upgrade of the Praha-Ruzyně–Kladno line, the longest stage of the Praha–Letiště–Kladno project; the award went to a consortium of Subterra, OHLA ŽS, Elektrizace železnic Praha and Swietelsky with a bid of CZK 8.279 billion (EUR 340 million), more than half a billion below the estimated value. The line, mostly on a new alignment, will be double-track and electrified and allows speeds of up to 145 km/h thanks to straightened curves; works were due to begin in spring 2026 and last until 2029, and according to a report of 22 December 2025 the administration had received the final building permit shortly before. The date is a placeholder: the article names only the year 2029 as the end of the building period; announced on 8 Apr 2026 (contract signing) (LOK Report, 8 Apr 2026; earlier report of 22 Dec 2025).
Source: lok-report.de ↗ · Archived copy ↗
Further sources: lok-report.de (22 Dec 2025) ↗ (Archived copy ↗)
Evidence: one source · based on reports (not independently confirmed) · archived copy saved · How well sourced is Eurotrack?