Dübendorf station raises platform for step-free access
- Location
- Dübendorf, Canton of Zurich · 🇨🇭 Switzerland
- Project
- Dübendorf Station Modernization (Platform Elevation)
- Investment
- CHF 5.7 million (platform elevation, financed via the federal performance agreement)
- Status
- Completed
As part of the "Railway Access 2023" (BZU23) program, SBB raised the central platform at tracks 3/4 in Dübendorf station to the new standard height of 55 cm to enable step-free, accessible boarding onto S-Bahn trains. Construction began in March 2020 and was scheduled for completion by the end of 2020, at a cost of CHF 5.7 million financed by the federal government via the performance agreement. After completion, the platform sector layout was revised and a new Sector F introduced (confirmed as of November 2020).
Source: zo-online.ch ↗ · Archived copy ↗