Baltic states synchronise power grid with continental Europe
- Location
- Estonia, Latvia, Lithuania · 🇪🇺 Europe
- Project
- Synchronisation of the Baltic power grid with the European grid
- Investment
- more than EUR 1.2 billion in EU funding (Connecting Europe Facility for Energy)
- Status
- Completed
Estonia, Latvia and Lithuania synchronised their electricity grids with the continental European grid in February 2025, disconnecting from the Russian-Belarusian BRELL system. The EU Commission supported the necessary infrastructure – including the LitPol Link (Poland), NordBalt (Sweden) and Estlink (Finland) interconnections – with more than EUR 1.2 billion from the Connecting Europe Facility for Energy. The date was moved up from the originally planned end of 2025.
Source: energy.ec.europa.eu ↗ · Archived copy ↗
Evidence: one source · archived copy saved · second source missing (two-source rule) · How well sourced is Eurotrack?