Swissgrid to replace Grynau–Siebnen line with new 380 kV line

· Energy / power grid

Location
Between Grynau and Siebnen, Lake Zurich/Linth Plain region (municipalities of Uznach and Tuggen, cantons of St. Gallen and Schwyz) · 🇨🇭 Switzerland
Project
Grynau–Siebnen grid line replacement (220 kV to 380 kV overhead line)
Investment
CHF 11.1 million
Status
In planning (approval procedure underway; partial section already completed)

Swissgrid is replacing the existing 220 kV overhead line between Grynau and Siebnen with a new 380 kV line spanning 5.2 km with 14 new pylons (52-83 m tall), closing a 5 km bottleneck in the transmission grid. The section between the Siebnen substation and pylon No. 915 has already been upgraded; the plan approval dossier submitted in 2020 is being re-displayed for public review, with a decision expected in 2026. Construction is planned for 2028/2029, with commissioning and dismantling of the old line scheduled for 2030; the investment volume is CHF 11.1 million.

Source: swissgrid.ch ↗ · Archived copy ↗

Evidence: one source · archived copy saved · How well sourced is Eurotrack?

✉ Report an error