Swissgrid expands Pradella–La Punt line to 380 kV

· Energy / power grid

Location
Engadin, Canton of Graubünden (Pradella–Zernez–La Punt) · 🇨🇭 Switzerland
Project
Pradella – La Punt grid project (upgrade to a 2×380 kV line)
Investment
CHF 120 million (project cost incl. compensatory measures, per Swissgrid)
Status
Completed / in operation

Swissgrid upgraded the roughly 50 km extra-high-voltage line between Pradella and La Punt in the Engadin (Canton of Graubünden) to carry two full 380 kV systems, since the pylons had previously carried a line on only one side. The upgraded line was commissioned on 11 November 2022, with total project costs including compensatory measures of CHF 120 million according to Swissgrid. As a compensatory measure, around 1,100 distribution pylons in the Engadin were also replaced by an underground 110 kV cable.

Source: swissgrid.ch ↗ · Archived copy ↗

Evidence: one source · based on reports (not independently confirmed) · archived copy saved · How well sourced is Eurotrack?