Ørsted completes Borssele I/II wind farm
- Location
- North Sea off Borssele, near the Belgian border, Netherlands · 🇳🇱 Netherlands
- Project
- Borssele I & II Offshore Wind Farm
- Investment
- not disclosed
- Status
- Operational
Borssele I & II is located in the Dutch North Sea about 24 km off the coast near Borssele, close to the Belgian border. It comprises 94 Siemens Gamesa turbines of 8 MW each (752 MW total capacity) and is operated by Ørsted. Construction started in January 2020, first power was generated in April 2020, and the farm was completed by the end of 2020; the official opening took place on 6 September 2021.
Source: en.wikipedia.org ↗ · Archived copy ↗