Eurotrack

Infrastructure

RFI activates ETCS Level 2 on the Monza–Chiasso line

· Transport / rail

Location
Lombardy, Monza–Chiasso line (Italy–Switzerland border) · 🇮🇹 Italy
Project
Milan–Chiasso: ETCS Level 2 (Monza–Chiasso section)
Investment
approx. EUR 6 million (RFI, for the 2022 activation); the original 2015 signalling contract for the full Milan–Monza–Chiasso line was worth approx. EUR 34 million
Status
Completed / operational (activated)

On 20 June 2022, RFI activated the ERTMS/ETCS Level 2 train control system on the Monza-Chiasso line, part of the Milan-Chiasso route on the Rotterdam-Genoa interoperable corridor. The investment for this activation was around EUR 6 million; the line is centrally monitored from the Milano Greco signal box. Full conversion had originally been planned for December 2018 (2015 contract with an Alstom-led consortium, worth approx. EUR 34 million), but was delayed by roughly three and a half years.

Source: rfi.it ↗ · Archived copy ↗

Evidence: one source · How well sourced is Eurotrack?

✉ Report an error

More from: 🇮🇹 Italy

Open in the tracker →