Swissgrid plans 380kV line from Innertkirchen to Ulrichen via Grimsel Pass

· Energy / power grid

Location
Grimsel Pass area between Innertkirchen (canton of Bern) and Ulrichen (canton of Valais), with roughly 23 km of underground cabling between Innertkirchen and Oberwald · 🇨🇭 Switzerland
Project
Innertkirchen–Ulrichen grid project: replacing the 220 kV line with a 380 kV extra-high-voltage line
Investment
not specified
Status
In planning – construction project stage (Q3 2025), Federal Council approval expected Q4 2027

Swissgrid is upgrading and reinforcing the roughly 27 km extra-high-voltage line between Innertkirchen (Bern) and Ulrichen (Valais) across the Grimsel Pass, raising the voltage from 220 to 380 kV. In February 2023 the Federal Council set a planning corridor with largely underground cabling over about 23 km between Innertkirchen and Oberwald (main option: cable tunnel; alternative: cable gallery parallel to the Grimsel rail tunnel). Per Swissgrid's schedule, tendering and construction run until Q4 2033, with commissioning planned by 2040 at the latest — later than the originally listed target year of 2034.

Source: swissgrid.ch ↗ · Archived copy ↗