Nauders substation links Austrian and Italian power grids

· Energy / power grid

Location
Nauders, Tyrol (border to South Tyrol/Glurns, Italy) · 🇦🇹 Austria
Project
Nauders substation (380/220 kV Reschen Pass interconnector Austria–Italy)
Investment
approx. EUR 91.5 million (APG share); plus approx. EUR 80 million on the Italian side invested by Terna
Status
Completed / in operation (initial activation December 2023, full operation since 6 June 2024)

The new 380/220 kV substation in Nauders, Tyrol, links via a roughly 27 km 220 kV line (1.2 km of it underground) to the Glurns/Glorenza substation in South Tyrol, forming the third electrical interconnection between Austria and Italy after 1952 and 2013. The line provides transmission capacity of up to 300 MW; Austrian Power Grid invested about EUR 91.5 million, with Terna investing a further EUR 80 million on the Italian side. Following initial activation in December 2023, the facility reached full operation on 6 June 2024.

Source: apg.at ↗ · Archived copy ↗