Celtic Interconnector Ireland–France delayed to end of 2028

· Energy / power grid

Location
Cork (Ireland) / Brittany (France) · 🇮🇪 Ireland / France
Project
Celtic Interconnector (subsea cable Cork–Brittany, EirGrid and RTE)
Investment
not specified (EU funding of €530m since 2019)
Status
Under construction, commissioning now expected in Q4 2028 according to EirGrid

Announced on 28 Apr 2026: The joint EirGrid and RTE project for Ireland's first power cable to continental Europe was due to go live in 2026; EirGrid's website now gives the fourth quarter of 2028 as the expected date. The cited power-systems professor blames mainly cable manufacturing and installation problems, adds that the date depends on weather and could slip further (Irish Examiner, 28 Apr 2026).

Source: irishexaminer.com ↗ · Archived copy ↗

Evidence: one source · archived copy saved · How well sourced is Eurotrack?

✉ Report an error

More from: 🇮🇪 Ireland · 🇫🇷 France