Banedanmark delays electrification of the Holbæk–Kalundborg line
- Location
- Holbæk–Kalundborg (Northwest Line), Region Sjælland, Zealand · 🇩🇰 Denmark
- Project
- Holbæk–Kalundborg railway electrification
- Investment
- not specified
- Status
- Under construction (site preparation), completion delayed
Banedanmark is electrifying the roughly 42 km Northwest Line between Holbæk and Kalundborg on Zealand, including about 500 catenary masts and two autotransformer stations (Regstrup, Jyderup); site preparation (clearing, land acquisition) is underway. According to a Banedanmark statement, the completion originally targeted for 2028 will not be met due to delays by the main contractor (Aarsleff Rail/Siemens) and knock-on delays from the Fredericia–Aarhus–Aalborg line; no new schedule has been confirmed yet.
Source: bane.dk ↗ · Archived copy ↗
Evidence: one source · archived copy saved · How well sourced is Eurotrack?