Eurotrack

Infrastructure

Saxony-Franconia line: Paditz–Lehndorf section completed

· Transport / rail

Location
Saxony, Leipzig–Hof line (Saxon-Franconian trunk line) between Altenburg and Crimmitschau/Lehndorf · 🇩🇪 Germany
Project
Paditz–Lehndorf upgrade
Investment
not specified
Status
Completed

The double-track Paditz–Lehndorf section of the Saxon-Franconian trunk line (Leipzig–Hof) was comprehensively modernised: a new electronic signal box, renewed overhead line equipment, three bridges, level crossings and noise barriers. Lehndorf station received two new 155 m platforms; the goal is to raise the permitted speed to up to 160 km/h. Construction began in 2017 in two phases, and Deutsche Bahn's project page now lists the section as completed.

Source: sachsen-franken-magistrale.de ↗ · Archived copy ↗

Evidence: one source · archived copy saved · How well sourced is Eurotrack?

✉ Report an error

More from: 🇩🇪 Germany

Open in the tracker →