Deutsche Bahn installs electronic interlockings and ETCS on POS North line

· Transport / rail

Location
Rhineland-Palatinate; northern branch Saarbrücken (border) – Ludwigshafen/Limburgerhof junction, approx. 128 km (lines 3250, 3280, 3401) · 🇩🇪 Germany
Project
POS North upgrade: electronic interlockings at Landstuhl, Kaiserslautern and Hochspeyer plus ETCS Level 2 to the Germany/France border – Limburgerhof
Investment
not specified
Status
Under construction (new interlockings and cabling work under way since 2024/2025; ETCS L2 equipping planned through 2029)

On the northern branch of the Paris–Budapest core corridor (TEN-T Corridor Atlantic) between the Germany/France border near Saarbrücken and the Limburgerhof junction (about 128 km, lines 3250/3280/3401), the interlockings at Landstuhl, Kaiserslautern Hbf and Hochspeyer are being replaced with modern electronic interlockings and fitted with ETCS Level 2 with signals (roughly 5,000 balises, 3 radio block centers). Cabling and construction work has been under way since 2024/2025 during live operations (including cabling between Hochspeyer and Landstuhl in June 2025), after which speeds of up to 200 km/h will be possible on some sections. Completion is planned for 2029; the investment volume is not publicly disclosed.