BARD Offshore 1 wind farm off Borkum with 400 MW is operational
- Location
- North Sea, approx. 100 km northwest of Borkum, Germany · 🇩🇪 Germany
- Project
- BARD Offshore 1 (offshore wind farm)
- Investment
- approx. EUR 3 billion (due to significant cost overruns)
- Status
- Operational
BARD Offshore 1 is located about 100 km northwest of Borkum in the North Sea and has an installed capacity of 400 MW from 80 BARD 5.0 turbines (5 MW each, 90 m hub height, 122 m rotor diameter). Construction was completed in July 2013 (official inauguration in August 2013); technical problems drove investment costs up to roughly EUR 3 billion, contributing to the project company's 2013 bankruptcy. It is operated by Ocean Breeze Energy GmbH & Co. KG, owned since 2019 by funds managed by Macquarie Asset Management.
Source: en.wikipedia.org ↗ · Archived copy ↗
Evidence: one source · archived copy saved · second source missing (two-source rule) · How well sourced is Eurotrack?