Amprion plans first power flow on Rhein-Main-Link from 2033
- Location
- Lower Saxony to Hesse · 🇩🇪 Germany
- Project
- Rhein-Main-Link (HVDC underground cable, about 600 km)
- Investment
- about €15bn
- Status
- Planning approval under way, construction currently planned to start in 2028
The roughly 600 km direct-current route is to bring offshore wind power to Hesse, ultimately up to eight gigawatts; Amprion expects costs of about €15bn. The planning approval application was filed on 27 Jun 2024, the first two gigawatts are to flow to Bürstadt from 2033, and further lines follow later until about 2039/2040. Only the year is documented, hence the placeholder date of 31 Dec. (hessenschau, 3 Mar 2026)
Source: hessenschau.de ↗ · Archived copy ↗
Evidence: one source · archived copy saved · second source missing (two-source rule) · How well sourced is Eurotrack?