Eurotrack

Under construction & planned

Deutsche Bahn expands Rhine Valley Railway sections near Basel

· Transport / rail

Location
Haltingen and Weil am Rhein (Baden-Württemberg, Germany) to Basel (Switzerland) · 🇩🇪 Germany
Project
Rhine Valley Railway upgrade Karlsruhe–Basel: planning sections 9.2 and 9.3 (Haltingen–Weil am Rhein & Basel)
Investment
approx. EUR 400 million (combined planning and construction budget for PFA 9.2 and 9.3, 2010 agreement)
Status
Under construction

The roughly 5 km PFA 9.2 section between Haltingen and Weil am Rhein is being expanded to six tracks (two each for long-distance, freight and regional traffic) with modernized stations at Haltingen and Weil am Rhein; construction began in 2011 and, per Wikipedia, completion is planned for end of 2028. The roughly 3.1 km PFA 9.3 section in Basel, entirely on Swiss territory (border to Badischer Bahnhof), has been under construction since June 2021 and is due to be completed mid-2028. A combined planning/construction budget of about EUR 400 million was agreed for both sections in 2010; the overall Karlsruhe–Basel project is estimated at roughly EUR 14.2 billion (as of May 2020).

Source: karlsruhe-basel.de ↗ · Archived copy ↗

Evidence: one source · based on reports (not independently confirmed) · archived copy saved · How well sourced is Eurotrack?

✉ Report an error

More from: 🇩🇪 Germany

Open in the tracker →