50Hertz plans Südostlink+ HVDC cable from Mecklenburg to Bavaria
- Location
- Mecklenburg-Vorpommern (starting near Klein Rogahn/Stralendorf/Warsow/Holthusen/Schossin) via Saxony-Anhalt, Saxony and Thuringia to the Isar grid connection point in Bavaria · 🇩🇪 Germany
- Project
- Südostlink+ (Project 5a): Klein Rogahn/Stralendorf/Warsow/Holthusen/Schossin – Isar
- Investment
- not specified
- Status
- In planning (route corridor fixed for some sections, permitting procedure ongoing)
Südostlink+ (Project 5a) is transmission operator 50Hertz's roughly 713 km HVDC underground cable route between the Klein Rogahn/Stralendorf/Warsow/Holthusen/Schossin grid connection points in Mecklenburg-Vorpommern and Isar in Bavaria, with 2 GW transmission capacity at ±525 kV. The route corridor for sections E and F was fixed on 30 May 2025; the planning approval procedure is still ongoing. Planned completion: 2030 (source states 713 km, differing from the 758 km figure in the source list).
Source: de.wikipedia.org ↗ · Archived copy ↗
Evidence: one source · archived copy saved · How well sourced is Eurotrack?