Amprion and TransnetBW to commission Ultranet power link in 2026

· Energy / power grid

Location
North Rhine-Westphalia – Baden-Württemberg (Meerbusch-Osterath to Philippsburg), approx. 340 km · 🇩🇪 Germany
Project
Ultranet: Osterath (NRW) – Philippsburg (Baden-Württemberg)
Investment
approx. EUR 1 billion (Amprion estimate from 2014)
Status
Under construction

Ultranet is a ±380 kV HVDC line with 2,000 MW transmission capacity running about 340 km between Meerbusch-Osterath (NRW) and Philippsburg (Baden-Württemberg), built by grid operators Amprion and TransnetBW largely along existing overhead-line routes. The Philippsburg converter station has been operating since late 2024 (initially as a STATCOM facility); construction of the line sections has been underway since autumn 2023. Full commercial operation of the link is planned for 2026.

Source: transnetbw.de ↗ · Archived copy ↗

Evidence: one source · archived copy saved · How well sourced is Eurotrack?

✉ Report an error

More from: 🇩🇪 Germany

Open in the tracker →